An energy project passes through three insurance lives, and the commonest mistake is treating them as
one: the developer's, processing permits and lodging guarantees with no asset yet; the
construction phase; and operation, which lasts decades.
The first guarantee comes before the first kilowatt
Article 23 of Royal Decree 1183/2020
conditions the access and connection application on first lodging a guarantee of €40 per kilowatt
installed. A 50 MW project means two million euros committed before there is anything to generate.
How that deposit is arranged is not an administrative footnote. The
Regulation of the General Deposit Office
admits a bank guarantee, surety insurance or government debt securities. The bank guarantee
consumes borrowing capacity exactly when it is needed to finance construction; surety insurance does
not. The detail is in the credit and surety page.
What costs money is not the part, it is the months
In operation the physical damage is usually the small part. A transformer or a gearbox has lead times
measured in months, and during those months the plant exports nothing. That is why the parameter that
decides whether the programme works is not the sum insured but the indemnity period of the
business interruption cover, which has to be sized against the manufacturer's real lead times rather
than a standard figure.
What the Electricity Sector Act does not say
Worth stating plainly, because the opposite circulates: Act 24/2013 does not require insurance.
The obligations come from elsewhere — the financial guarantee under
Act 26/2007 where the activity falls within
its Annex III, the civil liability insurance
Act 34/1998 requires in hydrocarbons before
work starts — and, above all, from the financing agreements, which tend to be considerably more
demanding than the statute.
Why through a broker
As a broker registered with the Spanish Directorate-General for Insurance and Pension Funds under
reference J0140, New Brokers works on the client's mandate, not on behalf of any insurer.
In energy the work is about synchronising three calendars that nobody synchronises on their own: the
permits and their guarantees, the construction and its acceptance, and the financing with its cover
requirements. The classic gap appears right at the seam between the construction policy and the
operational one, and it is closed before commissioning.